How Long Does It Take to Remove Asbestos from a Commercial Building? Insights from an Asbestos Removal Contractor in Chicago, Illinois

Written by :- Axis Response Group

November 24, 2025

If your commercial property has asbestos, how long will the removal process take? Below, this asbestos removal contractor in Chicago, Illinois is going to explore the main factors that influence the timeline of an asbestos removal project.

What makes some asbestos removal projects longer than others?

Some asbestos removal projects can be completed in a few days while others can take weeks. The duration mainly depends on what type of asbestos-containing materials are present and where they are in the building.

For example, removing a handful of ceiling tiles in a small office is a quick process. But clearing asbestos from a large warehouse can take much longer. A licensed asbestos removal contractor in Chicago, Illinois will need to inspect your building in person before they can give you an accurate estimate.

The condition and location of the asbestos are also important factors. If the material is crumbling or hidden behind walls or pipes, the removal will be slower and more deliberate. The removal team must keep the materials wet, seal off the area and make sure that no fibers escape into the air.

There is also some paperwork involved before the project even starts. In Illinois, large asbestos removal jobs require you to file a demolition or renovation notification at least ten business days before the project starts. If your property is located in Cook County, you will also need a special asbestos permit.

Your local asbestos removal contractor can guide you through the preparation process and handle the necessary filings for you.

What happens during an asbestos removal job?

An asbestos removal project is generally divided into four main stages:

First is the inspection and planning stage. A licensed asbestos inspector will visit your building, collect samples and assess the scope of the asbestos contamination. For a small space, this may only take one day. Once the inspection is complete, your asbestos removal contractor in Chicago, Illinois will create a removal plan with you.

Next is site preparation. Licensed technicians will isolate the contaminated area using plastic sheeting, shut down HVAC systems in that area, set up negative air machines and post warning signs. This step is crucial for containing asbestos fibers and protecting everyone on-site. Depending on the size of the space, this can take one to two days.

The third stage is the actual removal. Technicians will wet down the asbestos materials to prevent fibers from becoming airborne and carefully remove them. Every piece of contaminated material will be sealed in special bags and prepared for disposal. The duration of this stage depends entirely on the amount of asbestos present.

Once the asbestos is removed, technicians will clean the area using specialized vacuums and surface cleaners. An air quality test will then be performed to make sure the area is safe again. Only after passing this clearance test can the space return to normal use. This final stage generally takes about a day, but it can take longer for larger properties.

In total, a small commercial building can usually be remediated within five business days. Bigger properties or removal completed in phases can take anywhere from one to three weeks.

Looking for an asbestos removal contractor in Chicago, Illinois?

Are you searching for a trusted asbestos removal contractor in Chicago, Illinois that can handle everything from inspection and testing to safe removal and disposal? If so, look no further than Axis Response Group. Our licensed technicians can guide you through the entire process and make sure your building is asbestos-free as quickly and safely as possible. Contact us today at (773) 427-6811 to schedule a consultation or get a free on-site assessment.